Road Construction News
-
County Roads Half-Load Restrictions Come Into Effect March 2, 2026
Half-load season in our region will come into effect on Monday March 2, 2026.
-
NOTICE OF STUDY COMMENCEMENT - Highway 401 Planning Study
The Ontario Ministry of Transportation (MTO) has commissioned HDR Inc. to conduct a *Preliminary Design and Class Environmental Assessment (Class EA)* Study.
-
County Road 3 Road Closure - November 3-7, 2025
Temporary Road Closure for Culvert Replacement Location: County Road 3 (0.35 km south of County Road 33) Start Date: Monday November 3, 2025 End Date: Friday November 7, 2025 County Road 3 will be temporarily closed between County Road 33 and Red Horse Lake Road with no through access to replace a cross culvert beginning on Monday, November 3, 2025 to Friday, November 7, 2025.
-
County Road 7 Road Closure - September 29 - October 24, 2025
As part of the ongoing multi-phase road rehabilitation of County Road 7, the United Counties of Leeds and Grenville and Willis Kerr Contracting Ltd.
-
Lyndhurst Bridge - Construction Notice
Lane Width Restriction & Detour Advisory Location: Lyndhurst Bridge (County Road 33) Dates: Wednesday, August 27, 2025, to September 28, 2025 (4 weeks), excluding September 20.
-
County Road 22 - Temporary Road Closure - May 26-30, 2025
As a part of the ongoing rehabilitation of County Road 22 (South of Heckston) between County Road 20 (Norton Road/Dillabaugh Road) and Latimer Road, a temporary road closure is required and will be implemented to accommodate several cross-culvert replacements. The temporary road closure will be in place from May 26th until May 30th, 2025.
-
County Road 22 Road Construction – Spring/Summer 2025
This year, the United Counties of Leeds and Grenville and Green Infrastructure Partners (GIP, Inc.) will be rehabilitating approximately 2.
-
Half Load Restrictions Lifted on County Roads
Half load restrictions have been lifted on all County roads. As Spring/Summer road work is set to begin, please remember to drive safe and slow down in road work areas.
-
County Road 7 Road Construction – Spring/Summer 2025
This year, the United Counties of Leeds and Grenville and Tackaberry Construction will be rehabilitating approximately 7.5 kilometres of County Road 7 between County Road 16 and Kitley Line 8.
May 05, 2025
-
Next Phase of Westport Storm Sewer Outfall Project to Commence on April 28, 2025
The United Counties of Leeds and Grenville would like to inform the public that the next phase of the Westport Storm Sewer Outfall Project (PW-2024-23) will commence on April 28, 2025, and is expected to be completed before the end of May 2025.
-
Update - County Road 44 Road Closure New End Date - November 29, 2024
The United Counties of Leeds and Grenville have contracted Willis Kerr Contracting Ltd.
-
Update - County Road 44 Road Closure New End Date - November 22, 2024
The United Counties of Leeds and Grenville have contracted Willis Kerr Contracting Ltd. for the replacement of the Glen Smail box culvert on County Road 44.
-
County Road 13 Asphalt Paving - October 31 - November 1, 2024
Asphalt Paving Operations (base course / first lift), as part of the ongoing rehabilitation of County Road 13 between County Road 32 and the Kingston boundary, is planned to commence on Thursday, October 31, 2024 with an anticipated completion date of Friday, November 01, 2024.
-
County Road 42 Asphalt Paving – October 18, 21 - 23, 2024
Asphalt Paving Operations, as part of the ongoing rehabilitation of County Road 42 between Highway 15 in Crosby and Newboro (4.6 km), is planned to commence on Friday, October 18, 2024 and will continue on Monday, October 21, 2024, with an anticipated completion date of Wedneday, October 23, 2024.
-
County Road 30 Asphalt Paving – September 30 - October 3, 2024
Asphalt Paving Operations, as part of the ongoing rehabilitation of County Road 30 between County Road 29 and County Road 42 (4.7 km), is planned to commence on Monday, September 30, 2024 and is expected to be completed by Thursday, October 3, 2024.
-
County Road 44 Road Closure - September 30 to November 5, 2024
The United Counties of Leeds and Grenville have contracted Willis Kerr Contracting Ltd. for the replacement of the Glen Smail box culvert on County Road 44.
-
County Road 2 Alternating Lane Restrictions - October 2024
The United Counties of Leeds and Grenville has contracted Clarence McDonald Excavation Ltd. to replace a concrete box culvert at civic address 3209 on County Road 2 in Johnstown, ON.
-
County Road 13 Alternating Lane Restrictions - Fall 2024
This year, the United Counties of Leeds and Grenville and Tackaberry Construction will be rehabilitating approximately 2.5 kilometres of County Road 13 from County Road 32 to the Kingston boundary.
-
County Road 2 Road Closure - September 16-19, 2024
The United Counties of Leeds and Grenville have contracted G. Tackaberry & Sons Construction Co.
-
County Road 42 Lane Restrictions - September 9, 2024
Cold In-Place Asphalt Recycling construction activities, as part of the ongoing rehabilitation of County Road 42 between Highway 15 in Crosby and Newboro (4.6 km), is planned to commence on Monday, September 09, 2024.
-
County Road 22 Road Closure Update - End Date: September 20, 2024
County Road 22 at Hyndman Bridge - Nation River Road Updated Completion Date: September 20, 2024 As part of the ongoing rehabilitation of Hyndman Bridge, County Road 22 at this location will remain closed to traffic for a period not to exceed three (3) weeks, finishing no later than September 20, 2024.
-
County Road 30 Lane Restrictions - September 3-5, 2024
Cold In-Place Asphalt Recycling construction activities, as part of the ongoing rehabilitation of County Road 30 between County Road 29 and County Road 42 (4.7 km), is planned to commence on Tuesday, September 03, 2024 and is expected to be completed by Thursday, September 05, 2024.
-
County Road 42 Temporary Road Closure - August 12-16, 2024
As a part of the ongoing rehabilitation of County Road 42 between Highway 15 in Crosby and Newboro, a temporary road closure is required and will be implemented to accommodate several cross-culvert replacements.
-
County Road 42 Alternating Lane Restrictions - July 22 - November 30, 2024
This year, the United Counties of Leeds and Grenville and Tackaberry Construction will be rehabilitating approximately 4.6 kilometres of County Road 42 from Highway 15 to Newboro.
-
County Road 5 Road Closure - June 17-18, 2024
County Road 5 will be closed at the CN Tracks from Monday June 17th at 7:00 a.m.
-
County Road 30 Lane Restrictions - Beginning June 3, 2024
This year, the United Counties of Leeds and Grenville and Tackaberry Construction will be rehabilitating 4.7 kilometres of County Road 30 from County Road 29 to County Road 42.
-
County Road 15 Lane Restrictions - June 3-7, 2024
Location: County Road 15 - Approximately 5.1 km between North Augusta, ON and the Village of Merrickville-Wolford boundary.
-
County Road 3 Lane Restrictions - May 29-31, 2024
Location: County Road 3 - Lansdowne, ON - Approximately 2.7 km between Lansdowne railway tracks and highway 401 overpass.
-
Half Load Restrictions on Leeds Grenville County Roads
Half Load Restrictions were in effect on Leeds and Grenville County Roads from February 15th to May 15th and have now been lifted through all of the Counties. For more information, and to obtain any road-related permits, please contact the Public Works Department at 613-342-3840 Ext.
-
Media Release Dated March 13, 2023
Rideau Ferry Bridge Work to Continue Starting March 15 From March 15 to July 2023, traffic will be reduced to one lane on the Rideau Ferry Bridge during its ongoing rehabilitation.
-
Media Release Dated February 24, 2023
The highlights of the regular United Counties of Leeds and Grenville Council meeting held on Thursday, February 23rd, as well as the Joint Services Committee (JSC) meeting held earlier this month, are listed below.
-
Half Load Restrictions on Leeds Grenville County Roads (1)
Half Load Restrictions are in effect on Leeds and Grenville County Roads from February 15th to May 15th.
Feb 13, 2023
-
Media Release - Rideau Ferry Bridge Second Closure
Second Rideau Ferry Bridge Closure is set for November 24, 2022
Nov 17, 2022
Contact Us
United Counties of Leeds and Grenville
25 Central Ave. W, Suite 100
Brockville, Ontario K6V 4N6
Telephone: 613-342-3840
Toll Free: 1-800-770-2170
Sign up to our Newsletter
Fresh updates, straight to your inbox. Sign up now to stay informed about all things happening in the County.